Quinte Consolidated Courthouse

New-Image-profileLocation: Belleville

Project Type: DBFM - Design Build Finance Maintain

Infrastructure Type: Justice

Price of Contract: $247.2 million

Estimated Value for Money : $12.8 million


About the Project:  

  • The new courthouse will consolidate the Superior Court of Justice and Ontario Court of Justice, which are currently operating in four court locations: three in Belleville and one in Trenton.

 

Project Status

image

July 30, 2013

image

July 06, 2011

image

June 22, 2011 Brookfield Infrastructure Partnerships Quinte (BIPQ): Brookfield Financial Corp. and Morguard Corporation, with PCL Constructors Canada providing construction services. The facility was designed by WZMH Architects, with Morguard also providing facilities management. Brookfield Financial Corp. also acted as the financial advisor to Brookfield Partnerships Quinte.

image

May 13, 2010

image

April 13, 2010

image

August 31, 2009

 

Community and Green Benefits

  • Improve access to court services
  • Increase the number of available courtrooms
  • Provide better security
  • Better access for people with disabilities
  • Environmentally-friendly design features in order to achieve LEED Silver certification as part of the government’s commitment to reduce energy use and greenhouse gas emissions

Economic Benefits

  • At the peak of construction activity, it is estimated that 200 workers will be on the site daily

Media Gallery

Renderings 

 New-Image-thumb-renders 

Events 

 Quinte_Consolidated_Courthouse-32-thumb-events 

Terms of Use

These project documents are being made available on this Web site for informational purposes only. Neither Infrastructure Ontario nor the Ministry of the Attorney General makes any representation or warranty regarding the accuracy or completeness of the content or form of these documents.

 

Infrastructure Ontario and the Ministry of the Attorney General, in their sole and absolute discretion, may choose to make available on this Web site amendments, revisions, modifications or replacements to these documents. These documents remains open for further revision, modification, replacement or cancellation by Infrastructure Ontario and the Ministry of the Attorney General at any time and in no event shall either Infrastructure Ontario or the Ministry of the Attorney General be responsible or liable, directly or indirectly, for any damage or loss caused or alleged to be caused by or in connection with the use of or reliance on the content of these documents.