Kingston General Hospital
- Location:
- Kingston
- Project Type:
- BF - Build Finance
- Infrastructure Type:
- Health Care
- Contract Price:
- $142.1 million
- Estimated Value for Money:
- $19.8 million
About the Project
- The project involved 170,000 square feet of new construction and renovations to 143,000 square feet of the existing facility.
Status:
-
Request for QualificationsApr 02, 2007
-
Short-list Bidders SelectedJun 14, 2007
-
Request for ProposalsOct 09, 2007
-
Winning Bidder SelectedJul 10, 2008
-
Construction BeginsJul 14, 2008
-
Construction EndsDec 22, 2011
Latest News
Winning Bidder
PCL Constructors Canada Inc. and includes financing arranged by The Toronto-Dominion Bank
Features
- A consolidated and expanded hospital to provide more beds;
- A new acute mental health unit;
- An expanded and renovated Cancer Centre, with:
- two new radiation bunkers
- more than double the space for chemotherapy treatment
- a specialized clinic area for pediatric patients
- an overall environment that will enhance patients' privacy and dignit
- An expanded Intensive Care Unit with more beds (from 21 to 33 beds);
- Construction of a new, expanded 40-station, in-centre Kidney Dialysis Unit;
- New 25-bed unit for inpatient pediatrics;
- A new unit for 32 medical-surgical beds. The new unit consists of more single and isolation rooms than has been typical in existing units.
- Expanded and upgraded Central Processing Services, a key support to surgical services.
Community And Green Benefits
- The redevelopment project has created a more family-oriented environment and improved patients' access to care.
- The design and construction achieved the Leadership in Energy and Environmental Design (LEED®) Silver classification for incorporating environmentally sustainable construction practices and energy efficient design.
Economic Benefits
- Job creation for an estimated 75 workers on site daily at the peak of construction.
- Hundreds of thousands of dollars spent in the local community for construction and related supplies.
Terms of Use
These project documents are available for informational purposes only. Neither Infrastructure Ontario nor Kingston General Hospital makes any representation or warranty regarding the accuracy or completeness of the content or form of these documents.
Infrastructure Ontario and Kingston General Hospital, in their sole and absolute discretion, may choose to make available amendments, revisions, modifications or replacements to these documents. These documents remain open for further revision, modification, replacement or cancellation by Infrastructure Ontario and Kingston General Hospital at any time and in no event shall either Infrastructure Ontario or Kingston General Hospital be responsible or liable, directly or indirectly, for any damage or loss caused or alleged to be caused by or in connection with the use of or reliance on the content of these documents.
Related Links
Announcements
- Sign Unveiling - Feb. 2, 2007
- Request for Qualifications Issued - Apr. 4, 2007
- Short Listed Proponents Named - June 14, 2007
- Request for Proposals Issued - Oct. 5, 2007
- Request for Proposals Closed - Apr. 7, 2008
- Financial Close - July 10, 2008
- Construction work starts - Nov. 10, 2008
- Opening of new inpatient pediatric unit - Dec. 11, 2009
- Opening of new dialysis unit - Nov. 23, 2010
- Opening of new mental health unit - June 10, 2011
- Intensive Care Unit Opening - Dec. 2, 2011
- Substantial Completion - Apr. 10, 2012
- Substantial Completion - Backgrounder