Hamilton Health Sciences - Hamilton General Hospital
- Location:
- Hamilton
- Project Type:
- BF - Build Finance
- Contract Price:
- $44.9 million
- Estimated Value for Money:
- $7.2 million
About the Project
- Hamilton General Hospital's redevelopment gives local residents access to a wider range of rehabilitation services and consolidates the previous Acquired Brain Injury and Rehabilitation services from 14 locations to one site.
Status:
-
Request for QualificationsNov 03, 2006
-
Short-list Bidders SelectedFeb 21, 2007
-
Request for ProposalsMar 08, 2007
-
Winning Bidder SelectedSep 27, 2007
-
Construction BeginsOct 31, 2007
-
Construction EndsJul 09, 2009
Latest News
Winning Bidder
EllisDon Corporation, with financing arranged by CIBC and The Pacific and Western Bank of Canada
Features
- more than 100,000 square feet of new space in a three-storey wing
- increase in inpatient beds - from 414 to 458
- increase in rehabilitation beds - from 134 to 149
- more space to house all ambulatory programs and outreach service
- a therapy pool on the ground floor
- a new building tailored to meet rehabilitation patients needs
- fully accessible facility
- indoor and outdoor exercise facilities
- landscaped external therapy spaces on each level for a healing environment
Community And Green Benefits
- better access to rehabilitation services
- newer economic and employment opportunities for the local community
Economic Benefits
- At the peak of construction, more than 130 workers were on site daily.
Project Documents
The following documents are available upon request:
- Guaranteed Price Contract - Henderson
- Lender’s Direct Agreement - Henderson
- Limited Assignment of Construction Contract - Henderson
- Project Agreement
- Request for Proposals
- Value for Money Report
- Fairness Report
To request documents, please email: info@infrastructureontario.ca
Terms of Use
These project documents are available for informational purposes only. Neither Infrastructure Ontario nor Hamilton General Hospital makes any representation or warranty regarding the accuracy or completeness of the content or form of these documents.
Infrastructure Ontario and Hamilton General Hospital, in their sole and absolute discretion, may choose to make available amendments, revisions, modifications or replacements to these documents. These documents remain open for further revision, modification, replacement or cancellation by Infrastructure Ontario and Hamilton General Hospital at any time and in no event shall either Infrastructure Ontario or Hamilton General Hospital be responsible or liable, directly or indirectly, for any damage or loss caused or alleged to be caused by or in connection with the use of or reliance on the content of these documents.
Related Links
Announcements
- Request for Qualifications Issued - Nov. 3, 2006
- Short Listed Proponents Named - Feb. 21, 2007
- Request for Proposals Issued - Mar. 9, 2007
- Sign Unveiling - May 25, 2007
- Request for Proposals Closed - June 25, 2007
- Winning Bidder Named - Sept. 27, 2007
- Financial Close - Nov. 1, 2007
- Construction work starts - Nov. 9 2007
- Regional Rehabilitation Centre opens- Sept. 1, 2009