Markham Stouffville Hospital
- Location:
- Markham
- Project Type:
- BF - Build Finance
- Infrastructure Type:
- Health Care
- Contract Price:
- $200.4 million
- Estimated Value for Money:
- $24.3 million
About the Project
- Markham Stouffville Hospital (MSH) is the community hospital for Markham, Stouffville and Uxbridge, with two sites located in Markham and Uxbridge.
- The redevelopment project included a four-storey, 385,000 square feet addition, doubling, the size of the MSH facility.
Status:
-
Request for QualificationsOct 15, 2009
-
Short-list Bidders SelectedMar 19, 2010
-
Request for ProposalsMar 19, 2010
-
Winning Bidder SelectedDec 01, 2010
-
Construction BeginsDec 06, 2010
-
Construction EndsJul 24, 2014
Latest News
Winning Bidder
PCL Constructors advised by TD Securities, includes financing provided by The Toronto-Dominion Bank, Laurentian Bank of Canada, Canso Investment Counsel Ltd, and Alberta Investment Management Corporation.
Features
- A new emergency department
- Improved and expanded ambulatory clinics
- More inpatient beds and opearating rooms
- New diagnostic imaging department
- New maternal child area
- New mental health unit
Community And Green Benefits
- The expanded hospital offers the capacity for more emergency and ambulatory clinic visits and an increased number of inpatient beds.
- Markham Stouffville Hospital achieved Leadership in Energy and Environmental Design (LEED®) certification for construction of the new addition. LEED standards focus on healthy indoor environments, reduced greenhouse gas emissions and efficient use of energy, water and other resources.
Economic Benefits
- At the peak of construction activity, approximately 300 workers were on site daily, with 25 to 40 per cent of the workforce coming from the Region of York.
- The expanded hospital employs an additional 875 staff and attracted approximately 60 new physicians to the area.
Terms of Use
Project documents are available for informational purposes only. Neither Infrastructure Ontario nor Markham Stouffville Hospital makes any representation or warranty regarding the accuracy or completeness of the content or form of these documents.
Infrastructure Ontario and Markham Stouffville Hospital, in their sole and absolute discretion, may choose to make available amendments, revisions, modifications or replacements to these documents. These documents remain open for further revision, modification, replacement or cancellation by Infrastructure Ontario and Markham Stouffville Hospital at any time and in no event shall either Infrastructure Ontario or Markham Stouffville Hospital be responsible or liable, directly or indirectly, for any damage or loss caused or alleged to be caused by or in connection with the use of or reliance on the content of these documents.
Related Links
Announcements
- Architectural firm chosen - Aug. 13, 2007
- Request for Qualifications Issued - Oct. 15, 2009
- Request for Qualifications Closed - Jan. 18, 2010
- Request for Proposals Issued - Mar. 19, 2010
- RFP - Backgrounder
- Request for Proposals Closed - Aug. 12, 2010
- Financial Close - Dec. 1, 2010
- Financial Close - Backgrounder
- Construction work starts - Dec. 16, 2010
- Topping Off' ceremony - Dec. 16 2011
- New Wing Opening - Mar. 13, 2013