Runnymede Healthcare Centre
- Location:
- Toronto
- Project Type:
- BF - Build Finance
- Infrastructure Type:
- Health Care
- Contract Price:
- $63 million
- Estimated Value for Money:
- $10.8 million
About the Project
- Runnymede Healthcare Centre's redevelopment project resulted in the construction of a new, 180,000 square foot facility built on the Runnymede Healthcare Centre site to replace the older facility.
Status:
-
Request for QualificationsNov 03, 2006
-
Short-list Bidders SelectedMar 12, 2007
-
Request for ProposalsApr 03, 2007
-
Winning Bidder SelectedOct 01, 2007
-
Construction BeginsOct 29, 2007
-
Construction EndsMar 10, 2010
Latest News
Winning Bidder
Bondfield Construction Company Ltd. Financed by Ontario Teachers' Pension Plan and National Bank Financial
Features
- Replaced the existing facility with a new building that is almost four times its size.
- Increased capacity for up to 200 beds.
- Enhances clinical and medical services for:
- A full range of therapeutic services
- Physiotherapy and occupational therapy
- Communication, swallowing and audiology therapy
- Respiratory therapy
- Activation and recreation activities
- Social services
- Around the clock professional nursing and medical care
Community And Green Benefits
- The new facility addresses growing need for specialty services.
- Reduced wait times for the clinical and medical services.
Economic Benefits
- During construction, the project provided jobs to the estimated 100 workers who were on site daily.
Terms of Use
Project documents are available for informational purposes only. Neither Infrastructure Ontario nor Runnymede Healthcare Centre makes any representation or warranty regarding the accuracy or completeness of the content or form of these documents.
Infrastructure Ontario and Runnymede Healthcare Centre, in their sole and absolute discretion, may choose to make available amendments, revisions, modifications or replacements to these documents. These documents remain open for further revision, modification, replacement or cancellation by Infrastructure Ontario and Runnymede Healthcare Centre at any time and in no event shall either Infrastructure Ontario or Runnymede Healthcare Centre be responsible or liable, directly or indirectly, for any damage or loss caused or alleged to be caused by or in connection with the use of or reliance on the content of these documents.
Related Links
Announcements
- Request for Qualifications Issued - Nov. 3, 2006
- Short Listed Proponents Named - Mar. 12, 2007
- Short-Listed Proponents Named - Backgrounder
- Request for Proposals Issued - Apr. 3, 2007
- Request for Proposals Closed - Jul. 18, 2007
- Winning Bidder Named - Oct. 1, 2007
- Financial Close - Oct. 31, 2007
- Topping Off Ceremony - Oct 8, 2007
- Construction Work Starts - Nov. 7, 2007
- Grand Opening - Dec. 8, 2010